Notice to Guests from Busselton Water
Information Regarding 2nd Water Storage Tank Project
PLANT 4, NEW 4.5ML STORAGE TANK
Information Update- Mandalay Resort
GENERAL PROJECT INFORMATION
Where is Plant 4?
Busselton Water’s Plant 4 site is located at 381 Bussell Highway, Broadwater.
Why is this project needed?
Continued land development and associated population growth in the area has led to a steady increase in water supply requirements. The existing Plant 4 storage tank is not sufficient to meet future forecasted peak supply requirements. To meet future demand an additional 4.5ML tank will be installed adjacent to the existing tank.
What will the project involve?
The project involves four phases of works, with the following timeframes currently anticipated. Any changes to this schedule will be communicated with you as soon as possible.
https://www.busseltonwater.wa.gov.au/new-4-5ml-water-storage-tank-plant-4/
Phase Scope of Works Estimated Timeline
1 Site clearing to accommodate the new tank footprint. This includes removal of approximately 15 trees. AUG2024
2 Civil and piping works to prepare a pad and tank support structure. SEP2024-NOV2024
3 Site fabrication, erection and commissioning of the new 4.5ML steel tank. NOV2024-MAY2025
4 Installation and commissioning of mechanical components and pipework to connect the new tank to the existing supply network. APR2025-JUN2025
What are the community benefits of this project?
The benefits are increasing plant 4 water storage capacity which in turn reduces the risks of
supplying water to the community. The project focuses on reducing energy usage through more efficient operation of bores and transfer pumps at non-peak times. Finally the additional Tank will improve network reliability by allowing essential maintenance to occur without customers
experiencing outages.
Environmental and heritage impacts?
Busselton Water is working with expert consultants to ensure that appropriate flora, fauna and environmental surveys are undertaken, and that the results are considered in the planning and design for the project.
Our environmental consultants are progressing the necessary approvals and permits with the relevant State and Federal Government agencies.
To support the local community and sustainability, the trees removed during the site clearing in AUG2024 are intended to be donated to a local community group.
What to expect during construction works?
Below are general items to expect during construction works:
• All work will occur on Busselton Water’s Plant 4 site. Contractor on-site working hours are expected to be 7:00am to 6:00pm on weekdays. There may be occasional works on Saturday’s. If required, advance notification can be provided.
• There will be construction noise throughout the works, which will be managed in accordance with the City of Busselton regulations.
Below are high level target schedule dates at present. Starting 14OCT.
Civil/Piping Activities |
Estimated Start |
Estimated Finish |
Notes |
Civil equipment mobilizing to site |
17OCT |
17OCT |
|
Tree root ball extraction |
23OCT |
24OCT |
Likely to be periodic high noise during this work as each tree is extracted. |
Excavation of tank foundation |
25OCT |
30OCT |
|
Compaction of ring beam base |
31OCT |
01NOV |
Due to space, plate compactors are required. Will be high noise. |
Formwork and concrete for ring beam |
04NOV |
20NOV |
|
Compaction of tank base |
21NOV |
27NOV |
|
Asphalt sealing of base |
04DEC |
05DEC |
|
Install pipework and valves |
02APR |
23MAY |
|
Demobilise |
28MAY |
28MAY |
|
Tank Activities |
Estimated Start |
Estimated Finish |
Notes |
Materials and equipment delivery to site |
02DEC |
03DEC |
|
Install floor plates |
07JAN |
20JAN |
Crane on site. Welding and periodic grinding throughout. |
Install wall plates |
21JAN |
28MAR |
Crane on site. Welding and periodic grinding throughout. |
Install roof structure |
28MAR |
26APR |
Crane on site. Welding and periodic grinding throughout. |
Internal and external coatings |
27APR |
30MAY |
Spot blasting will be required along all of the plate weld margins. Will be periodic high noise. |
Commissioning |
02JUN |
09JUN |
|
Demobilise |
10JUN |
10JUN |
|
Proposed actions to limit negative impact to surrounding properties?
Busselton Water propose to take the below actions to limit negative impact to Mandalay Resort:
• Provide Mandalay Resort with a schedule of works for the upcoming week every Monday by 8am.
• Install 2.1m high temporary construction fencing along the northern property boundary.
• Complete as much steel sand blasting in the fabrication shop as feasible.
• Limit site sand blasting works to after 9am.
• Setup 7m high posts and shade cloth surrounding the north side of the new tank during construction works.
• Utilise a water cart to limit dust.
General Site Layout
Next Steps
Further project updates will be provided in advance of each of the four construction phases.
We are committed to delivering a successful project for the benefit of the community. Should you have questions at any point please don’t hesitate to contact me via email at
conor.gill@busseltonwater.wa.gov.au or phone at 0400 300 947.